Panama Canal claims $737m in cost overruns

Almaghrib Today, almaghrib today

Almaghrib Today, almaghrib today Panama Canal claims $737m in cost overruns

Panama Canal
Panama City - AFP

The consortium building the third set of locks for the Panama Canal is making fresh claims for cost overruns totaling $737 million, officials said Friday.
Canal administrator Jorge Quijano told reporters that the Panama Canal Authority had received two claims on Tuesday that "will be evaluated" to determine if there is probable cause.
But he warned that "at first glance, the issues will be very difficult for the counterparty to justify."
One of the claims, for $333 million, is related to the weight of the gate for the locks -- at 55,000 tonnes, compared to the 35,000 tonnes initially planned.
But Quijano pointed to a clause in the contract, according to which the canal authority would pay up to the value of a gate weighing 49,000 tonnes.
The second claim, for $404 million, is due to delays in the fourth phase of excavation in the Pacific sector.
The consortium, Grupos Unidos por el Canal, says that the delay in excavation work may mean it will not receive water needed to test the gates.
Quijano, however, said he has a "plan B" to provide the necessary water for testing.
The canal authority will pay another $120 million in adjustments to the contract and other small claims, Quijano said.
Work began in 2007 to expand the canal with a third set of locks to enable it to handle the modern mega-freighters that global shipping companies prefer.
But the $5.25 billion project has been plagued by delays, strikes and a bitter dispute over $1.6 billion in cost overruns with the consortium carrying out the upgrade, led by Spanish construction firm Sacyr.
Initially scheduled for completion in 2014, the project's due date has been pushed back to early 2016.
Nearby Nicaragua, meanwhile, launched construction this week on a rival canal, a $50 billion project that the Chinese firm behind it plans to complete in five years.

 

almaghribtoday
almaghribtoday

Name *

E-mail *

Comment Title*

Comment *

: Characters Left

Mandatory *

Terms of use

Publishing Terms: Not to offend the author, or to persons or sanctities or attacking religions or divine self. And stay away from sectarian and racial incitement and insults.

I agree with the Terms of Use

Security Code*

panama canal claims 737m in cost overruns panama canal claims 737m in cost overruns

 



Name *

E-mail *

Comment Title*

Comment *

: Characters Left

Mandatory *

Terms of use

Publishing Terms: Not to offend the author, or to persons or sanctities or attacking religions or divine self. And stay away from sectarian and racial incitement and insults.

I agree with the Terms of Use

Security Code*

panama canal claims 737m in cost overruns panama canal claims 737m in cost overruns

 



Almaghrib Today, almaghrib today Skincare PR Performance Full Year 2017

GMT 09:22 2018 Monday ,22 January

Skincare PR Performance Full Year 2017
Almaghrib Today, almaghrib today New hunt for flight MH370 gets under way

GMT 11:03 2018 Wednesday ,24 January

New hunt for flight MH370 gets under way
Almaghrib Today, almaghrib today Modern colorful bedroom renovation

GMT 10:57 2017 Thursday ,21 December

Modern colorful bedroom renovation
Almaghrib Today, almaghrib today Puigdemont candidate for Catalan president

GMT 13:56 2018 Tuesday ,23 January

Puigdemont candidate for Catalan president
Almaghrib Today, almaghrib today Turkey detains dozens more

GMT 10:47 2018 Wednesday ,24 January

Turkey detains dozens more

GMT 09:57 2016 Wednesday ,23 March

cartoon two

GMT 10:22 2016 Wednesday ,23 March

cartoon twelve

GMT 10:20 2016 Wednesday ,23 March

cartoon ten

GMT 09:58 2016 Wednesday ,23 March

cartoon four

GMT 09:56 2016 Wednesday ,23 March

cartoon one

GMT 10:22 2016 Wednesday ,23 March

cartoon thirteen

GMT 10:18 2016 Wednesday ,23 March

cartoon eight

GMT 10:17 2016 Wednesday ,23 March

cartoon six

GMT 10:18 2016 Wednesday ,23 March

cartoon seven

GMT 10:24 2016 Wednesday ,23 March

cartoon fifteen

GMT 10:19 2016 Wednesday ,23 March

cartoon nine

GMT 09:58 2016 Wednesday ,23 March

cartoon three

GMT 10:16 2016 Wednesday ,23 March

cartoon five

GMT 10:23 2016 Wednesday ,23 March

cartoon fourteen

GMT 10:21 2016 Wednesday ,23 March

cartoon eleven

GMT 13:44 2017 Tuesday ,29 August

Power demand to peak in Europe summers, not winters
Almaghrib Today, almaghrib today
 
 Almaghrib Today Facebook,almaghrib today facebook  Almaghrib Today Twitter,almaghrib today twitter Almaghrib Today Rss,almaghrib today rss  Almaghrib Today Youtube,almaghrib today youtube  Almaghrib Today Youtube,almaghrib today youtube

Maintained and developed by Arabs Today Group SAL.
All rights reserved to Arab Today Media Group 2025 ©

Maintained and developed by Arabs Today Group SAL.
All rights reserved to Arab Today Media Group 2025 ©

.almaghribtoday .almaghribtoday .almaghribtoday .almaghribtoday
almaghribtoday almaghribtoday almaghribtoday
almaghribtoday
بناية النخيل - رأس النبع _ خلف السفارة الفرنسية _بيروت - لبنان
almaghribtoday, Almaghribtoday, Almaghribtoday