Only 49 days are left for the inauguration of the new Suez Canal project, the Armed Forces said on Thursday.
Dry digging operations at the main canal line were over after lifting 250 million cubic meters, the army said in a statement.
The statement added that further 70 million cubic meters have been dug to expand el Ballah bypass to become 312 meters wide.
A total of 225 million cubic meters of water-saturated sand have so far been lifted at the project.
The figure represents 87.2 percent of the target of 258 million cubic meters.
About 39 dredgers are operating at the waterway.
GMT 17:47 2018 Monday ,15 January
‘Negative’ outlook for Gulf sovereign ratings in 2018, says Moody’sGMT 19:27 2018 Sunday ,07 January
UAE pledges to distribute 70% of VAT proceeds to help fund community projectsGMT 19:21 2018 Sunday ,07 January
Surge in foreign fund inflows sets stage for Egyptian boomGMT 19:15 2018 Sunday ,07 January
Iraq to export Kirkuk oil to Iran before January-endGMT 11:35 2018 Wednesday ,03 January
Saudi Food and Drug Authority: No VAT on human medicines, vitamins, and registered medical equipmentGMT 10:00 2018 Wednesday ,03 January
Saudi Customs launches Approved Economic Operator programGMT 07:30 2018 Wednesday ,03 January
Morocco’s 2017 Economic Growth: GDP on the Rise, Investment in DeclineGMT 18:33 2018 Monday ,01 January
No New Year cheer for UAE property market
Maintained and developed by Arabs Today Group SAL.
All rights reserved to Arab Today Media Group 2025 ©
Maintained and developed by Arabs Today Group SAL.
All rights reserved to Arab Today Media Group 2025 ©
Send your comments
Your comment as a visitor