Nearly 93.73 percent of dredging works have been finalized in the New Suez Canal project, said a report issued by the executive authority of the Suez Canal Project.
Up to 244.409 million cubic meters of water-saturated sand have been dredged so far as part of the Suez Canal Development Project, the report said.
A total 258 million cubic meters should be dredged as part of the project, the report added.
Thirty-four degraders are currently working in Egypt’s giant
project.
In the meantime, Ismailia governor continued field tours in the new project to follow up preparation for the inauguration of the new canal, slated for August 6.
GMT 17:47 2018 Monday ,15 January
‘Negative’ outlook for Gulf sovereign ratings in 2018, says Moody’sGMT 19:27 2018 Sunday ,07 January
UAE pledges to distribute 70% of VAT proceeds to help fund community projectsGMT 19:21 2018 Sunday ,07 January
Surge in foreign fund inflows sets stage for Egyptian boomGMT 19:15 2018 Sunday ,07 January
Iraq to export Kirkuk oil to Iran before January-endGMT 11:35 2018 Wednesday ,03 January
Saudi Food and Drug Authority: No VAT on human medicines, vitamins, and registered medical equipmentGMT 10:00 2018 Wednesday ,03 January
Saudi Customs launches Approved Economic Operator programGMT 07:30 2018 Wednesday ,03 January
Morocco’s 2017 Economic Growth: GDP on the Rise, Investment in DeclineGMT 18:33 2018 Monday ,01 January
No New Year cheer for UAE property market
Maintained and developed by Arabs Today Group SAL.
All rights reserved to Arab Today Media Group 2025 ©
Maintained and developed by Arabs Today Group SAL.
All rights reserved to Arab Today Media Group 2025 ©
Send your comments
Your comment as a visitor