Nearly 96.58 percent of dredging works have been finalized in the New Suez Canal project, said a report issued by its executive authority.
Up to 254.740 million cubic meters of water-saturated sand have been dredged so far as, the report said.
A total 258 million cubic meters should be removed as part of the project, the report added.
Thirty dredgers are currently working in Egypt’s giant project.
The total length of the project is 72 km, according to the website of the Suez Canal Authority.
The project will increase the daily average of transiting vessels to 97 ships by the year 2023, up from 49 ships at present.
It will also achieve direct unstopped transit for 45 ships in the two directions.
The venture will increase the Suez Canal revenues from $ 5.3 billion at present to $ 13.226 billion in 2023; an increase equal to 259% that shall positively contribute to Egypt’s national income of hard currencies.
GMT 17:47 2018 Monday ,15 January
‘Negative’ outlook for Gulf sovereign ratings in 2018, says Moody’sGMT 19:27 2018 Sunday ,07 January
UAE pledges to distribute 70% of VAT proceeds to help fund community projectsGMT 19:21 2018 Sunday ,07 January
Surge in foreign fund inflows sets stage for Egyptian boomGMT 19:15 2018 Sunday ,07 January
Iraq to export Kirkuk oil to Iran before January-endGMT 11:35 2018 Wednesday ,03 January
Saudi Food and Drug Authority: No VAT on human medicines, vitamins, and registered medical equipmentGMT 10:00 2018 Wednesday ,03 January
Saudi Customs launches Approved Economic Operator programGMT 07:30 2018 Wednesday ,03 January
Morocco’s 2017 Economic Growth: GDP on the Rise, Investment in DeclineGMT 18:33 2018 Monday ,01 January
No New Year cheer for UAE property market
Maintained and developed by Arabs Today Group SAL.
All rights reserved to Arab Today Media Group 2025 ©
Maintained and developed by Arabs Today Group SAL.
All rights reserved to Arab Today Media Group 2025 ©
Send your comments
Your comment as a visitor